853 source observations describing buildings, campuses, utility projects and generating plants. Compare reported quantities with their original scope and date.
A service agreement states what a customer may receive. An IT rating describes computing capacity. A generator rating describes generation capacity. Each answers a different question. These research observations do not establish actual demand or operating status.
Search operator specifications, utility agreements, SEC and FERC filings, EIA generator records, and ISO load datasets. MISO announcement summaries remain labelled informational leads. Source publication dates and retrieval dates remain separate from the date a quantity applies. Multiple documents from one operator are not independent confirmation. Crypto mining and names without a confirmed data center classification remain separately labelled.
853 source observations. Showing 36. Overlapping observations cannot be added into a power total.
interconnection load project · dated load record
1 Gig Data Center East Fishkill, NY
Source location: Dutchess, NY. Building position remains unverified.
1,000 MW
Requested peak load
Source labels Peak MW load. A requested project peak, not metered demand or guaranteed service.
Quantity role: requested project load boundary not proven facility total.
Source identifier 1738.
Source status: SRIS/SIS in Progress
Source proposed date 10-2026. This is not an observed opening.
Source classification
data center. Native source label or bounded name screen; not an independent classification audit.
Source effective date 2026-08-31. Publication date not identified; actual retrieval remains separate.
This is not a measured demand observation.
Source limits and unresolved issues
No street/building location except where the project name explicitly supplies one. POI locations are not facility coordinates.
Queue status and proposed backfeed date do not prove data-center commissioning or actual demand.
Requests may be phases, uprates or alternative projects. Do not sum or divide them among buildings.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com ↗iso load interconnection queue. Publication date not supplied. Retrieved 2026-09-17.
Sheet Load Projects · cell E48.
SHA-256 8158c0eb16ef93ce0a4f9f0dd8316d5680edbefbaeaab3758d7eded2e53c8e9b
interconnection load project · dated load record
1 Gig Data Center East Fishkill, NY
Source location: not provided. Building position remains unverified.
1,000 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · summer.
Source identifier 1738.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Oct-28. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
interconnection load project · dated load record
1 Gig Data Center East Fishkill, NY
Source location: not provided. Building position remains unverified.
950 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · winter.
Source identifier 1738.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Oct-28. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
load facility not resolved to building · dated load record
1547 CSR - Orangeburg LLC
Source location: not provided. Building position remains unverified.
30 MW
Reported existing load
Explicitly stated in Table IV-7 footnote; no arithmetic, PUE or allocation.
Quantity role: existing load.
Source identifier 1715.
Source status: existing as reported
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Resulting total is conditional on the requested uprate. It is not verified metered peak or IT load.
A native load facility can span multiple buildings. Exact building identity remains unresolved.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
1 source reference
www.nyiso.com · PDF page 137 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
load facility not resolved to building · dated load record
1547 CSR - Orangeburg LLC
Source location: not provided. Building position remains unverified.
60 MW
Reported resulting total load
Explicitly stated in Table IV-7 footnote; no arithmetic, PUE or allocation.
Quantity role: resulting total load.
Source identifier 1715.
Source status: proposed uprate as reported
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Resulting total is conditional on the requested uprate. It is not verified metered peak or IT load.
A native load facility can span multiple buildings. Exact building identity remains unresolved.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
1 source reference
www.nyiso.com · PDF page 137 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
load facility not resolved to building · dated load record
1547 CSR - Orangeburg LLC
Source location: not provided. Building position remains unverified.
30 MW
Reported load increase
Explicitly stated in Table IV-7 footnote; no arithmetic, PUE or allocation.
Quantity role: uprate increment.
Source identifier 1715.
Source status: proposed uprate as reported
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Resulting total is conditional on the requested uprate. It is not verified metered peak or IT load.
A native load facility can span multiple buildings. Exact building identity remains unresolved.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
1 source reference
www.nyiso.com · PDF page 137 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
interconnection load project · dated load record
1547 CSR - Orangeburg LLC
Source location: Rockland, NJ. Building position remains unverified.
30 MW
Requested peak load
Source labels Peak MW load. A requested project peak, not metered demand or guaranteed service.
Quantity role: requested project load boundary not proven facility total.
Source identifier 1715.
Source status: Accepted Cost Allocation/IA in Progress
Source proposed date 03-2027. This is not an observed opening.
Source classification
data center. Native source label or bounded name screen; not an independent classification audit.
Source effective date 2026-08-31. Publication date not identified; actual retrieval remains separate.
This is not a measured demand observation.
Source limits and unresolved issues
No street/building location except where the project name explicitly supplies one. POI locations are not facility coordinates.
Queue status and proposed backfeed date do not prove data-center commissioning or actual demand.
Requests may be phases, uprates or alternative projects. Do not sum or divide them among buildings.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
source state NJ conflicts with Orangeburg Rockland context
1 source reference
www.nyiso.com ↗iso load interconnection queue. Publication date not supplied. Retrieved 2026-09-17.
Sheet Load Projects · cell E30.
SHA-256 8158c0eb16ef93ce0a4f9f0dd8316d5680edbefbaeaab3758d7eded2e53c8e9b
interconnection load project · dated load record
1547 CSR - Orangeburg LLC
Source location: not provided. Building position remains unverified.
30 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: uprate increment · summer.
Source identifier 1715.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Jan-27. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
interconnection load project · dated load record
1547 CSR - Orangeburg LLC
Source location: not provided. Building position remains unverified.
30 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: uprate increment · winter.
Source identifier 1715.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Jan-27. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
1547 CSR Orangeburg name aligns. Source state NJ conflicts with Rockland/Orangeburg NY. No source street or building boundary.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
customer · allocation as reported
1547 CSR - Orangeburg, LLC / Orangeburg, NY
800 kW
public power allocation
Recharge New York allocation, not utility service limit or facility design. Name-and-city discovery association only. Two Orangeburg allocation rows remain separate. No building match or sum assumed.
Source effective date 2026-07-01. Row data_valid_as_of 7/1/2026.
Electrical extent: award program only.
This is not a measured demand observation.
Source limits and unresolved issues
Not selected for a pipeline scalar by immutable parent review.
1 source reference
nypa_dataset_rows ↗public registry. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d22fdb16f42f9987df5576181905ce9d4153541952c2fc100a905229f6da5411
customer · allocation as reported
1547 CSR - Orangeburg, LLC / Orangeburg, NY
400 kW
public power allocation
Recharge New York allocation, not utility service limit or facility design. Name-and-city discovery association only. Two Orangeburg allocation rows remain separate. No building match or sum assumed.
Source effective date 2026-07-01. Row data_valid_as_of 7/1/2026.
Electrical extent: award program only.
This is not a measured demand observation.
Source limits and unresolved issues
Not selected for a pipeline scalar by immutable parent review.
1 source reference
nypa_dataset_rows ↗public registry. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d22fdb16f42f9987df5576181905ce9d4153541952c2fc100a905229f6da5411
planned second building expansion · generator context
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
60 MW
Expansion generator capacity
Operator expansion description; generator capacity explicitly labeled.
Quantity role: planned expansion.
Source status: planned second building expansion at page retrieval
Source proposed date 2026. This is not an observed opening.
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Do not substitute expansion MW or generator capacity for facility demand.
This is the webpage description, not a reviewed video or evidence of completed construction.
1 source reference
www.1547realty.com ↗1547-expansion-video. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 4d42aea8489420b8810f20514393f2135aef9d4dd176f3b067faa0d7ef5f141b
planned second building expansion · load evidence
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
30 MW
Expansion power with an unspecified basis
Operator expansion description; 30MW electrical basis is not specified.
Quantity role: planned expansion.
Source status: planned second building expansion at page retrieval
Source proposed date 2026. This is not an observed opening.
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Do not substitute expansion MW or generator capacity for facility demand.
This is the webpage description, not a reviewed video or evidence of completed construction.
1 source reference
www.1547realty.com ↗1547-expansion-video. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 4d42aea8489420b8810f20514393f2135aef9d4dd176f3b067faa0d7ef5f141b
facility power system unspecified · power system context
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
12 MW
Onsite power with an unspecified basis
Operator native label: 12 MW on-site
Quantity role: operator labeled capacity.
Source status: undated live operator page at retrieval
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Redundancy, provisioned power and substation capacity do not prove total facility demand.
Different power bases on the same page are not interchangeable.
1 source reference
www.1547realty.com ↗1547-orny1. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 a87d342aacb66f703d9abf7cc16887a71dc7888f7e10dc7f484c157c1a40e861
named facility not resolved to polygon · it context
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
1.9 MW
Operator-reported IT capacity
Operator native label: Critical IT load: 1.9 MW
Quantity role: operator labeled capacity.
Source status: undated live operator page at retrieval
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Redundancy, provisioned power and substation capacity do not prove total facility demand.
Different power bases on the same page are not interchangeable.
1 source reference
www.1547realty.com ↗1547-orny1. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 a87d342aacb66f703d9abf7cc16887a71dc7888f7e10dc7f484c157c1a40e861
facility power system unspecified · power system context
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
24 MW
Provisioned power
Operator native label: 24 MW provisioned in an N+2 scheme
Quantity role: operator labeled capacity.
Source status: undated live operator page at retrieval
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Redundancy, provisioned power and substation capacity do not prove total facility demand.
Different power bases on the same page are not interchangeable.
1 source reference
www.1547realty.com ↗1547-orny1. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 a87d342aacb66f703d9abf7cc16887a71dc7888f7e10dc7f484c157c1a40e861
on site substation · power system context
1547 ORNY1
Source location: Orangeburg, NY. Building position remains unverified.
50 MW
Substation capacity
Operator native label: On-site substation with 50 MW capacity
Quantity role: operator labeled capacity.
Source status: undated live operator page at retrieval
Source classification
data center. source_native
Effective date not established. Printed meeting/filing date if supplied; otherwise unknown, inspect captured source.
This is not a measured demand observation.
Source limits and unresolved issues
Redundancy, provisioned power and substation capacity do not prove total facility demand.
Different power bases on the same page are not interchangeable.
1 source reference
www.1547realty.com ↗1547-orny1. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 a87d342aacb66f703d9abf7cc16887a71dc7888f7e10dc7f484c157c1a40e861
customer · allocation as reported
365 Data Centers NY One LLC / Commack, NY
2,850 kW
public power allocation
Recharge New York allocation, not utility service limit or facility design. Name-and-city discovery association only. Two Orangeburg allocation rows remain separate. No building match or sum assumed.
Source effective date 2026-07-01. Row data_valid_as_of 7/1/2026.
Electrical extent: award program only.
This is not a measured demand observation.
Source limits and unresolved issues
Not selected for a pipeline scalar by immutable parent review.
1 source reference
nypa_dataset_rows ↗public registry. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d22fdb16f42f9987df5576181905ce9d4153541952c2fc100a905229f6da5411
interconnection load project · dated load record
580 STAMP load increase
Source location: Genesee, NY. Building position remains unverified.
300 MW
Requested peak load
Source labels Peak MW load. A requested project peak, not metered demand or guaranteed service.
Quantity role: requested project load boundary not proven facility total.
Source identifier 1484.
Source status: Under Construction
Source proposed date 05-2028. This is not an observed opening.
Source classification
data center. Native source label or bounded name screen; not an independent classification audit.
Source effective date 2026-08-31. Publication date not identified; actual retrieval remains separate.
This is not a measured demand observation.
Source limits and unresolved issues
No street/building location except where the project name explicitly supplies one. POI locations are not facility coordinates.
Queue status and proposed backfeed date do not prove data-center commissioning or actual demand.
Requests may be phases, uprates or alternative projects. Do not sum or divide them among buildings.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com ↗iso load interconnection queue. Publication date not supplied. Retrieved 2026-09-17.
Sheet Load Projects · cell E17.
SHA-256 8158c0eb16ef93ce0a4f9f0dd8316d5680edbefbaeaab3758d7eded2e53c8e9b
interconnection load project · dated load record
580 STAMP load increase
Source location: not provided. Building position remains unverified.
300 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · summer.
Source identifier 1484.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Nov-26. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
interconnection load project · dated load record
580 STAMP load increase
Source location: not provided. Building position remains unverified.
300 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · winter.
Source identifier 1484.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Nov-26. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
building · proposed
AVAIO Pittsburg Data Hub
71.4 MW
Expected facility demand
Source explicitly reports this quantity in the design/PUE paragraph; no calculated PUE or utilization adjustment. Average ambient conditions at design IT load.
Source effective date 2024-02-29. CEC docket filed date; not HTTP Last-Modified
This is not a measured demand observation.
Source limits and unresolved issues
The same paragraph reports PUE 1.51 and 1.17, inconsistent with its stated load pairs. Preserve reported loads; no scalar promotion until reviewed.
1 source reference
building · proposed
AVAIO Pittsburg Data Hub
92 MW
Total facility design power
Source explicitly reports this quantity in the design/PUE paragraph; no calculated PUE or utilization adjustment.
Source effective date 2024-02-29. CEC docket filed date; not HTTP Last-Modified
This is not a measured demand observation.
Source limits and unresolved issues
The same paragraph reports PUE 1.51 and 1.17, inconsistent with its stated load pairs. Preserve reported loads; no scalar promotion until reviewed.
1 source reference
building · proposed
AVAIO Pittsburg Data Hub
60 MW
Critical IT capacity
Source explicitly reports this quantity in the design/PUE paragraph; no calculated PUE or utilization adjustment.
Source effective date 2024-02-29. CEC docket filed date; not HTTP Last-Modified
This is not a measured demand observation.
Source limits and unresolved issues
The same paragraph reports PUE 1.51 and 1.17, inconsistent with its stated load pairs. Preserve reported loads; no scalar promotion until reviewed.
1 source reference
announced project or campus unspecified · informational announcement
AWS / Becker, MN
Source location: not provided. Building position remains unverified.
383 MW
Announced load
MISO informational compilation of public announcements. The table does not identify underlying primary facility documents.
Quantity role: announced load location.
Source status: announced load location
Source proposed date TBA. This is not an observed opening.
Source classification
source labels data center. Native source label or bounded name screen; not an independent classification audit.
Source effective date 2024-12-06. Printed updated December 6, 2024; HTTP modification date is not the fact date.
This is not a measured demand observation.
Source limits and unresolved issues
MISO explicitly says this is not its forecast and is not intended for reliance or planning.
Full-load timing is TBD. Opening labels do not date attainment of load. Building scope is not established.
Informational lead only. Requires an underlying primary facility or utility filing before canonical power acceptance.
Informational compilation excluded from canonical quantity proposals even if an operator/locality matches.
1 source reference
cdn.misoenergy.org · PDF page 2 ↗iso public announcement compilation. Published 2024-12-06. Retrieved 2026-09-17.
SHA-256 e313b8d0199e6046e8a9aa93e55d4cdfefc3e427a44fa0564d4d77c65d7d66f0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
32 MVA
Utility-reported Lot 1 service, apparent power
Utility report summarizes assigned AWS service allocation for 2315 Mission College Boulevard.
Quantity role: conditional total service capacity · 2034.
Source status: city report summary of existing agreement; reported agreement assignment
Source classification
data center. source_native
Source effective date 2024-07-09. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Corroborates original Lot 1 contract; not additive to that schedule.
1 source reference
santaclara.legistar.com · PDF page 3 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 3441adb822cdcbbc5e41df2463fe4bc3db9cad682954b7a34e2718ed91ca71e5
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
9 MVA
Utility-reported Lot 1 service, apparent power
Utility report summarizes assigned AWS service allocation for 2315 Mission College Boulevard.
Quantity role: conditional total service capacity · initial as reported July 9, 2024.
Source status: city report summary of existing agreement; reported agreement assignment
Source classification
data center. source_native
Source effective date 2024-07-09. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Corroborates original Lot 1 contract; not additive to that schedule.
1 source reference
santaclara.legistar.com · PDF page 3 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 3441adb822cdcbbc5e41df2463fe4bc3db9cad682954b7a34e2718ed91ca71e5
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
14 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Lot 1 Substation Facilities Energization Date.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
32 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Lot 1 Substation Facilities Energization Date + 10 years.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
40 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Lot 1 Substation Facilities Energization Date + 15 years.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
49.5 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Lot 1 Substation Facilities Energization Date + 20 years.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
23 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Lot 1 Substation Facilities Energization Date + 5 years.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
customer service lot · load evidence
AWS Freedom Circle Lot 1
Source location: 2315 Mission College Boulevard, Santa Clara, CA. Building position remains unverified.
9 MVA
Original Lot 1 total service, apparent power
Table E1 Total Available Capacity for Lot 1, not Phase Added Capacity.
Quantity role: conditional total service capacity · Substation Agreement Date.
Source status: historical customer signed form later city report confirms agreement; customer signed city fields blank in attachment
Source classification
data center. source_native
Source effective date 2021-06-22. Council agenda date unless signed original specifies earlier effective date; exact public upload date unknown; publication date unknown
This is not a measured demand observation.
Source limits and unresolved issues
Utility service schedule, not measured consumption, IT load or total building design load.
Conditions, load reduction rights and later amendments may affect delivery. A date in a schedule does not prove capacity was delivered.
No MVA-to-MW conversion. No campus-to-building allocation. Parent retains canonical promotion.
Calendar dates are not inferred from the relative energization schedule. A separate 2024 utility report gives 2034 for 32 MVA.
Lot 2 capacity is TBD. Shared 99 MVA substation equipment is not the entitlement for either lot.
1 source reference
santaclara.legistar.com · PDF page 23 ↗municipal utility customer service. Publication date not supplied. Retrieved 2026-09-17.
SHA-256 d0c2709a9e9cffa287ad557c9f0811d472c63054cde7ca316ebb26713ad118d0
announced project or campus unspecified · informational announcement
AWS* / New Carlisle, Indiana
Source location: not provided. Building position remains unverified.
660 MW
Announced load
MISO informational compilation of public announcements. The table does not identify underlying primary facility documents.
Quantity role: announced load location.
Source status: announced load location
Source proposed date TBA. This is not an observed opening.
Source classification
source labels data center. Native source label or bounded name screen; not an independent classification audit.
Source effective date 2024-12-06. Printed updated December 6, 2024; HTTP modification date is not the fact date.
This is not a measured demand observation.
Source limits and unresolved issues
MISO explicitly says this is not its forecast and is not intended for reliance or planning.
Full-load timing is TBD. Opening labels do not date attainment of load. Building scope is not established.
Informational lead only. Requires an underlying primary facility or utility filing before canonical power acceptance.
Informational compilation excluded from canonical quantity proposals even if an operator/locality matches.
1 source reference
cdn.misoenergy.org · PDF page 2 ↗iso public announcement compilation. Published 2024-12-06. Retrieved 2026-09-17.
SHA-256 e313b8d0199e6046e8a9aa93e55d4cdfefc3e427a44fa0564d4d77c65d7d66f0
interconnection load project · dated load record
Alcoa East Energy Allocation Project
Source location: not provided. Building position remains unverified.
200 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · summer.
Source identifier 1751.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Jul-27. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
interconnection load project · dated load record
Alcoa East Energy Allocation Project
Source location: not provided. Building position remains unverified.
200 MW
Seasonal requested load
Table IV-7 seasonal request MW. Footnote 3 says these are queue values. Not necessarily baseline forecast or measured consumption.
Quantity role: request boundary unspecified · winter.
Source identifier 1751.
Source status: load interconnection request as reported in 2026 Gold Book
Source proposed date Jul-27. This is not an observed opening.
Source classification
data center. screening from later queue end-use; Gold Book does not print end-use
Source effective date 2026-03-15. Title pages state Released April 2026. Report says data as of March 15, 2026 unless otherwise noted.
This is not a measured demand observation.
Source limits and unresolved issues
Proposed in-service dates are not actual opening dates. Seasonal MW must remain separate.
Rows with notes 4-8 are increments, not the resulting facility total. Phase/campus/building scope is unresolved.
No exact code and primary street-address link to a mapped building established in this tranche.
1 source reference
www.nyiso.com · PDF page 136 ↗iso load interconnection queue. Published 2026-04. Retrieved 2026-09-17.
SHA-256 43865c1cbe38ca2ef4c8319d11454881de2b9dde3e48867dbbd2e94855b908bf
Assistant extraction from public documents. Building matches and scalar fields undergo separate review. This catalog adds no buildings or MW to the atlas totals. No default PUE or allocation of a campus total to its buildings is used.