← All researchPRIMARY DOCUMENT DOSSIER
Polaris Forge 1
Applied Digital · North Dakota
Document extraction only. These are dated source claims. We have not independently verified current construction or operating status.
Campus and building outlines still need location review. Do not attach these claims to Applied Digital's separate Harwood site.
Read the quantities in context.
The campus total includes the delivered building phases. These observations are not additive. The July release describes more delivered capacity than the April filing. That is a dated update, not automatically a contradiction. None of these figures establishes total facility electricity demand.
AS OF 2026-04-08
Building ELN-02
100 MW
Power, basis unspecified · Reported
Company reports completed and operating. The cited sentence does not specify facility versus IT power.
Status in this observation: Operating
Fiscal Q3 2026 earnings release, SEC exhibit on issuer website ↗AS OF 2026-04-08
Second building, full planned capacity
150 MW
Power, basis unspecified · Planned
Under construction in the April update, with expected delivery in 2026. Do not equate the plan with capacity already operating.
Status in this observation: Under construction
Fiscal Q3 2026 earnings release, SEC exhibit on issuer website ↗AS OF 2026-07-01
Building 2, phase 1
75 MW
Reported AI capacity · Reported
Company reports ready for service for this phase. Preserve the reported AI capacity wording without treating it as facility demand.
Status in this observation: Ready for service
Building 2 delivery announcement ↗AS OF 2026-07-01
Campus, live capacity
175 MW
Reported AI capacity · Reported
Campus total includes previously delivered capacity. This is not additional to the building figures.
Status in this observation: Partially operating
Building 2 delivery announcement ↗AS OF 2026-07-01
Campus, contracted full buildout
400 MW
IT capacity · Contracted
The company explicitly identifies critical IT load for the contracted full buildout. This is not a current operating total.
Status in this observation: Mixed phases
Building 2 delivery announcement ↗Document record
A capture fingerprint identifies the fetched document. It does not verify the truth of the author's claims. These quantities do not enter the atlas's power totals or completeness counts.